Monday, June 19, 2006

 

Shelf Moving on Fourth Floor

Bester Brothers has returned to begin moving the shelving on the fourth floor into its new configuration. The process should take about two days, and be completed by the end of the day tomorrow.


Tuesday, June 13, 2006

 

Fourth Floor Collection Moves

Some of the collections on the west side of the fourth floor, more specifically some of the Hs on the existing single-sided shelving, have been moved to a temporary shelving location on the southwest side of the floor. Signs on the existing shelves will tell you where the collections have moved. If you have difficulty, pick up and fill out a "Construction Zone Request Form" at the Circulation Desk and we will locate the book for you and notify you that it is ready to be picked up. Retrieved materials will be located at the Circulation Desk.

 

Demolition of Fifth Floor Complete


The walls are down on the fifth floor quiet study and the group and faculty studies. Carpet patching on fifth will happen later this week. On to the fourth floor...

Monday, June 12, 2006

 

Demolition on First Floor Complete

Demolition is now complete on the first floor. Workers will be working on the fifth floor today and the fourth floor later in the week.

Monday, June 05, 2006

 

Construction Begins


Dell arrived this morning to begin the demolition of several areas in the library which will be renovated. Pictured is demolition of the Government publications office area.