Preliminary Timetable for Summer Library Building Projects

Demolition will begin next week and take place on all floors - first, fourth, and fifth floors - simultaneously.

Construction will take place primarily between the hours of 7 a.m. and 3:30 p.m.

Construction of the new walls in different areas is supposed to start June 21.

Dell projects the compact shelving in the new Special Collections area will be installed relatively early in August.

The completion date for the new instructional lab is August 4.

The completion date for the remodeling of the classrooms (2023A, B and C) is August 18.

There will be emergency doors installed just beyond the Family Friendly Study. Dell agreed in the meeting to build the wall but hold off on installing the doors as long as possible so users will have continued access to LILL in its current location until the equipment has been moved to its new first floor location.